Sports hall refurbishment
11 January 2021
Work continued this week on the refurbishment of Priory’s sports hall.
Phase 1 has already been completed with the installation of new LED lighting. Phase 2 will be new flooring which started before the Christmas break and will finish w/c 11 January. The photos below show fresh layers being applied with one making it look like it's a swimming pool! After a final layer the line markings are added.
Phase 3 will begin mid-January with the repainting of the walls.
More photos of its progress will follow in the coming weeks.
Once completed the hall will match the standards of our other modern sports and assembly facilities, and will also be available for public lettings.